You need about
1,163 cubic yards of fill dirt
73truck loads of fill, 16 cu yd each
150tons of gravel on top, 8 loads
How this was worked out
- Corners A, B, C, D average 39 in deep, plus 6 in of topsoil taken off
- Pad: 100 ft × 60 ft × 45 in ÷ 12 ÷ 27 = 833 cu yd
- Side slopes at 3 to 1, four sides and four corners = 208 cu yd
- 1,041 cu yd − 111 cu yd of topsoil spread back on the slopes = 930 cu yd
- 930 cu yd ÷ 0.8 (dirt shrinks 20% when packed) = 1,163 cu yd
- 1,163 cu yd ÷ 16 cu yd a load, rounded up = 73 loads
- Topsoil taken off: 100 ft × 60 ft × 6 in ÷ 12 ÷ 27 = 111 cu yd
- Gravel: 100 ft × 60 ft × 6 in ÷ 12 ÷ 27 = 111 cu yd
- 111 cu yd × 1.35 tons a cubic yard = 150 tons
- 150 tons ÷ 20 tons a load, rounded up = 8 loads
The ground is taken as flat between the points you measured. Truck loads are rounded up so you are not one short.
-
About building pads
A fill pad is built up from the ground. Measure how deep the fill has to be at each corner. The page adds the pad, the sloped sides round it, and the hole left where the topsoil came off.
Dirt shrinks when it is packed hard. Georgia's road department works out dirt to bring in as the packed amount divided by 1 minus the shrink. At 20 percent shrink that is a quarter more dirt, not a fifth.
Dirt dug out of the ground fluffs up by about a quarter in the truck, so loads hauled off are counted at 1.25 times the dug amount.
Grass slopes should be no steeper than 2 to 1, and 3 to 1 or flatter where they get mowed. Building specs often call for at least 6 inches of topsoil to come off first.
For a big job, or a building that needs a permit, have an engineer or surveyor check the numbers.