How many bags for a paver patio?
Measure the patio. You get bags of paver base, leveling sand and polymeric sand, the joint sand mixed with a glue-like powder that hardens once it is wet.
Example numbers. Type your own.
You need about
84 bags of paver base
17bags of leveling sand
bags of polymeric sand
41.66cu ft of base, with the extra
8.33cu ft of leveling sand
How this was worked out
- Patio: 10 ft × 10 ft = 100 sq ft
- Base: 100 sq ft × 4 in ÷ 12 = 33.33 cu ft
- 33.33 cu ft × 1.25 (25% extra for packing down) = 41.66 cu ft
- 41.66 cu ft ÷ 0.5 cu ft a bag = 83.32 → 84 bags, rounded up
- Leveling sand: 100 sq ft × 1 in ÷ 12 = 8.33 cu ft
- 8.33 cu ft ÷ 0.5 cu ft a bag = 16.66 → 17 bags, rounded up
Each figure is rounded to 2 places, and the next line starts from it. Bags are rounded up, so the job does not come up one short.
-
About paver patio bags
Paver base is crushed stone and rock dust that packs hard. A patio wants about 4 inches of it under the pavers, more where the ground stays soft or wet.
Base shrinks as it is packed down with a hand tamper or a plate machine, so buy more than the depth alone works out to. How much more depends on the stone and on how hard it is tamped. That is what the extra box is for.
Leveling sand is the inch the pavers sit on, smoothed flat before they go down. Some bags call it bedding sand. It is not the sand that fills the joints.
Polymeric sand is swept into the joints once the pavers are laid. How far a bag goes depends on how wide the joints are and how big the pavers are, so read the bag and type its number in the box.
Past about a cubic yard of base, a bulk load is usually easier than a stack of bags. The crusher run calculator works out a bulk load.