How much asphalt and stone for a driveway?
Measure the drive, say what the ground is like and set your truck. You get the stone base, the hot mix and the loads of each.
Example numbers. Type your own.
You need about
13.9 tons of asphalt
16.4tons of stone
8.9cubic yards of stone, rolled
1truck load of asphalt, 63% full
1truck load of stone, 75% full
for the asphalt
How this was worked out
- Area: 60 ft × 12 ft = 720 sq ft ÷ 9 = 80 sq yd
- Asphalt: 80 sq yd × 110 lb × 3 in ÷ 2,000 = 13.2 tons
- 13.2 tons × 1.05 (5% extra for waste) = 13.9 tons
- 13.9 tons ÷ 22 tons a truck = 1 truck load of asphalt, 63% full
- Stone: 720 sq ft × 4 in ÷ 12 ÷ 27 = 8.89 cu yd rolled
- 8.89 cu yd × 1.85 tons a rolled cu yd = 16.4 tons
- 16.4 tons ÷ 1.4 tons a loose cu yd = about 11.7 loose cubic yards to order
- 16.4 tons ÷ 22 tons a truck = 1 truck load of stone, 75% full
Both thicknesses are after rolling. Truck loads are rounded up for each, so neither comes up one short.
-
About an asphalt driveway
The starting thicknesses come from a paving association's guide for home driveways. For most yards it calls for 3 inches of hot mix over 4 inches of stone, and 6 inches of stone on soft ground. With no stone under it, the guide calls for 4.5 to 5.5 inches of asphalt alone.
Every thickness here is measured after rolling. Clay that pumps squeezes up and moves under a loaded truck, so count it as poor ground.
Stone packs down when it is rolled. A cubic yard delivered loose weighs about 1.4 tons, the number the crusher run calculator uses, and the same stone rolled in place comes to about 1.85 tons. Rolled, real rock runs 1.7 to 1.9 tons, so change the stone weight if the quarry gives you theirs. That is why the loose yards to order are more than the rolled yards, and why the stone gets no waste line: you order the weight it has once packed, so nothing is lost to settling.
Run a turnaround or an apron as its own rectangle and add it on. Give the drive a fall of 1/4 inch for every foot so water runs off. A thin layer on a cool day leaves the crew only minutes to roll it, so pave in warm weather.