How much concrete for a footing?
Type the length of the footing, its width and its thickness. You get yards and bags.
Example numbers. Type your own.
You need about
37 bags of 80 lb concrete
0.81cubic yards
22cubic feet with the extra
for this job
How this was worked out
- 40 ft × (12 in ÷ 12) × (6 in ÷ 12) = 20 cu ft
- 20 cu ft × 1.1 (10% extra for waste) = 22 cu ft
- 22 cu ft ÷ 27 = 0.81 cu yd
- 22 cu ft ÷ 0.60 cu ft an 80 lb bag, rounded up = 37 bags
A footing is worked out as a long box. Bags are rounded up, so you do not come up one short.
-
About footings
A footing is the strip of concrete under a wall or a row of posts. It spreads the weight out into the ground. Type how far the strip runs in feet, then how wide and how thick it is in inches.
The footing size, and how deep below ground it has to sit, are set by your building inspector and local code, so ask them before you dig. One Tennessee county code sheet shows 12 inches wide by 6 inches thick for many small houses, with the bottom at least 12 inches below undisturbed ground. The same sheet asks for 8 inches thick for wider spread footings, one more reason to check first.
The math here is length times width times thickness, with the inches divided by 12 to make feet. The extra for waste goes on top, the total is divided by 27 for yards, and by what one bag makes for the bag count, rounded up.
If the footing turns a corner or steps down, work out each straight run on its own and add them.