How much asphalt and tack coat for an overlay?
Measure the area, set the new layer's thickness after rolling and what you are paving over. You get hot mix tons, tack gallons and the loads.
Example numbers. Type your own.
You need about
11.6 tons of asphalt
10.7gallons of tack
1truck load, 53% full
133square yards
for the asphalt
How this was worked out
- Area: 100 ft × 12 ft = 1,200 sq ft ÷ 9 = 133.33 sq yd
- Asphalt: 1,200 sq ft ÷ 9 × 110 lb × 1.5 in ÷ 2,000 = 11 tons
- 11 tons × 1.05 (5% extra for waste) = 11.55 tons → 11.6 tons
- 11.6 tons ÷ 22 tons a truck = 0.53 → 1 truck load, 53% full
- Tack coat: 1,200 sq ft ÷ 9 × 0.08 gal a sq yd, undiluted = 10.67 gal → 10.7 gal of tack
- 10.7 gal ÷ 231 = 0.05 tons of tack (how a state bid counts it)
The thickness is after rolling, and the tack rate is for undiluted tack. Truck loads round up to whole trucks.
-
About overlays
An overlay is a fresh layer of hot mix laid on a surface that is still sound underneath. On a driveway it is usually 1.5 to 2 inches after rolling. Fix the cracks and holes before you pave, or they show back through the new layer.
The tack coat is a thin, sticky spray of liquid asphalt that glues the new layer to the old one. Its rate is gallons of undiluted product for each square yard. State specs give a range, and the box starts at the middle of it. Tack is often sold watered down, and the water does no gluing, so ask how much of the tank is water and count only the rest.
A milled surface, with the top ground off, is rough and soaks up more. Fresh asphalt laid the same week takes less, and concrete a little less than old asphalt. Dividing the gallons by 231 gives tons, the unit a state bid uses.
Past about 4 inches it is new paving, not an overlay: start from the calculators on the Asphalt page.