How much comes off when you mill?
Measure the area and the depth you are milling. You get tons of millings, the loose pile and the truck loads to haul it.
Example numbers. Type your own.
Coming off, about
110 tons of millings
5truck loads
62.7loose cubic yards in the pile
55.6cubic yards in place
How this was worked out
- Area: 300 ft × 30 ft = 9,000 sq ft ÷ 9 = 1,000 sq yd
- Millings: 9,000 sq ft ÷ 9 × 110 lb × 2 in ÷ 2,000 = 110 tons
- In place: 9,000 sq ft × 2 in ÷ 12 ÷ 27 = 55.56 → 55.6 cu yd
- Loose pile: 110 tons × 2,000 ÷ 130 lb a cu ft ÷ 27 = 62.68 → 62.7 cu yd loose
- 110 tons ÷ 22 tons a truck = 5 truck loads
Millings weigh what the pavement weighed, so the tons use the paving rule. The loose pile is worked from the tons shown. Truck loads round up to whole trucks.
-
About milling
A milling machine grinds the worn top off an old road or lot so new asphalt can go down at the right height. What it leaves behind is millings, the crumbled old asphalt.
Nothing is lost when it is ground up, so the millings weigh what that layer of pavement weighed. That is why the tons here use the same rule as paving, run the other way.
Once ground, the same weight takes up more room, so the pile in the truck is bigger than the hole it came from. The research we used says millings run 120 to 140 pounds a cubic foot, but it does not say loose or packed. Start at 130, and if a scale ticket tells you different, put your number in.
Millings off a wet job weigh more, and a truck hits its weight limit before its bed is full, so plan loads by tons. Many crews sell millings or give them away for driveways. The other paving and upkeep jobs are on the Asphalt page.